baby's room

Looks like baby's room will be masculine! It's a boy!! woo hoo.

More pics of the house to come later this week. Windows are in, roof is on, chimney going up, spray-in insulation happening now.

Tuesday, April 21, 2009

our famed architect and his mini! Matthew and Rock Evans Hufft...


more pics
















LOOKING LIKE A REAL HOUSE!
















So, besides the obvious fact that I am a blogging deliquent, there hasn't been much obvious progress over the last month. They did the electrical and plumbing work, and prepped the roof and fireplace, but nothing that excited me too much:)!










But behold, what a difference a couple of weeks makes! Read below for the exciting "goings-on!!"










Metal roof is on and looks AMAZING. It was the best material choice we've made. Not only does it look great, but it will last 100+years. They trimmed the square dormers yesterday-those are SWEET. They give the house a real modern flare.










Windows go in today and tomorrow. We have TONS of windows, so that will really be a noticeable addition.










They delivered the brick/stone for the fireplace and chimney on Friday and the masons will put that up this week.










Siding should also start soon. Spray-in insulation is going in soon too. After that is done, they will begin drywall. Drywall should take a month or so. After drywall is hardwood floors-tile in mudroom and bathrooms.










After drywall is complete and the floors are in, cabinets will be installed. Then, just the last bit of infill.










This place is really coming together!